Milestone & Achievements

Take a Look at Our Achievements

We are proud to have successfully completed various pipeline and process projects. Explore our successful projects and get a glimpse of our expertise in pipeline and process solutions.
Flushing of 20” Kolocreek Rumuekpe Trunk Line.
SPDC – 2011

Work Scope

  • Dislodgement of Blockage on the trunk line

Execution

  • Deployment of flushing spread to dislodge the blockage (Sand/Stuck
MDF Pig).

Result

The Line was free of debris.

Routine pigging is recommended.

Acid Pickling Operation: Ogbainbiri Gas Plant
NAOC - 2023

Work Scope

  • Acid Pickling of Booster Pump

Execution

  • Acid Pickling using Pressure Pumps and Break/Holding Tanks

Result

Successful Cleaning of Booster Pump.

Pump optimization for Crude Transfer

Crude Oil and Condensate Pumping: Obagi Field
Total - 2022

Work Scope

  • Re-injection of Crude Oil

Execution

  • Pump using High-Pressure Pumps and Break/Holding Tanks

Result

Successful reinjection

Continuous Pumping optimization

Continuous Pumping/Fire Suppression for well kill services - Obodo Field
CONOIL - 2022

Work Scope :
Continous Pumping/ Fire Suppresion for Well Kill Services

Execution:
Deployment of Multi-Stage CP Pumps for Fire Suppression /Cooling during Well Kill Services

Results:
Successfully suppressed the fire.

Optimization of the CP Pumps for fire Cooling /Suppression